Skip to main content
The 1978 work programme, as approved by the Interim Mekong Committee, conforms to the general framework of the Indicative Basin Plan The programme is composed of 30 projects which, in turn, may be sub divided into 78 separate activities The projects fall into the following sectoral groups :

Hydrology and meteorology 3
Basin planning 8
Projects relating to the mainstream 2
Tributary projects 9
Navigation improvement 5
Agriculture and fisheries 3

These 30 projects which have been operational or partly operational in 1978 have been executed on behalf of the Committee either by agencies of the participating governments and co operating countries and organizations, by consulting firms, by the Committee’s Secretanat, or by combinations of some of these bodies working in collaboration.