| The Third Meeting
of the Working Party on the Application of New
Technology to Population Data |
| Bali, 7-9
January 1999 |
STAT/WPA(3)/Rec
12 January 1999
ECONOMIC AND SOCIAL COMMISSION FOR ASIA AND THE
PACIFIC
Working Party on the Application of New Technology
to Population Data
Third Meeting
7-9 January 1999
Bali |
| Recommendations
of the Third Meeting of the Working Party on the
Application of New Technology to Population Data |
| Contents |
| I.
Major Recommendations of the Working Party
Workshop
on the application of IT to Population Data |
|
I.
Major Recommendations of the Working Party |
The Working Party welcomed Mr
Koki Toida as a new member to replace outgoing
Mr Akihito Yamauchi, who also attended and who
had already been reassigned to the Personnel
Bureau of the Management and Coordination Agency,
Japan.
The major recommendations adopted by the Working
Party in its third meeting are listed below. |
|
| Recommendations
regarding the work underway |
- In view of the recommendation
of the mid-term review of the project that
a workshop be convened in October 1999, the
Working Party stressed the importance of producing
outputs well ahead of the Workshop.
- In reviewing and revising
the outlines of the three guidelines in the
light of its previous discussions on their
scope and the pressing time constraint, the
Working Party recommended that:
- the titles of the three
guidelines be as follows:
- "Guidelines
on the application of new information
technology to population data dissemination"
- "Guidelines
on the application of modern mapping
and GIS technologies in census operations"
- "Guidelines
on the application of new technology
to population data collection and
capture"
- the guidelines should
be restricted to new technology, have
a sharp focus, and generally not go beyond
the point where a particular technology
ceases to have an impact.
- the guidelines should
have a preambular section that specifies
their scope, context and intended audience,
underlying philosophy and principles,
and provide the minimum necessary background
information
- editors be appointed
to collate, harmonize and edit the guidelines.
The editors may be experts engaged as
consultants under the project, members
of the working party or staff members
of NSOs represented in the Working Party.
- he editors should be
allowed to exercise flexibility in interpreting
the revised outlines, in determining the
final structure, and in adjusting the
titles of the guidelines.
- for each guideline,
contributions were required from its members.
- the guidelines should
draw from best practices found useful
in applying information technology in
NSOs.
- the guidelines should
help NSOs particularly in developing countries
to apply the latest feasible information
technology rather than be driven by the
information technology per se
- all guidelines should
contain a glossary of technical terms
and acronyms, and a disclaimer on the
scope (e.g. intended/selected comprehensiveness).
- The Working Party decided
on the tentative outlines for the guidelines
as follows:
|
| Guidelines on the application
of new technology to population data collection
and capture |
| Overall coordinator: Indonesia |
|
| Section |
Contributors |
| I. |
Introduction |
Indonesia |
| II. |
Internet data collection |
Singapore |
| III. |
CAPI |
Australia |
| IV. |
CATI |
- Singapore (responsible
for obtaining and compiling section inputs)
- Australia
|
| V. |
Imaging technology, including OMR and OCR |
- Indonesia (responsible
for obtaining and compiling section inputs,
and for drafting a section on OCR)
- Japan (section on OMR)
- New Zealand (section
on work flow issues related to imaging)
- Australia (section
on combining imaging and autocoding)
|
|
|
|
| Guidelines on the application
of modern mapping and GIS technologies in census
operations |
| Overall coordinator: Bangladesh |
| Section |
Contributors |
| I. |
Need for digital geographic information (= introduction) |
Bangladesh |
| II. |
GPS |
Bangladesh |
| III. |
GIS |
Philippines |
|
| Guidelines on the Application
of New Technology to Population Data Dissemination |
| Overall coordinator: New Zealand
(with Singapore as backup) |
- Introduction
- Statistical information
systems for dissemination
- GIS
- Internet for dissemination
- Other modes of dissemination
through electronic media, Diskettes, CD-ROM,
etc.
|
- The Working Party agreed
that technology sections of all three guidelines
should deal with the following issues, for
which the material presented in the Working
Party meetings offered a good starting point:
- Explain concepts necessary
to understand the technology and the objectives
of applying it
- Cover requirements
for planning and training to put the technology
in place and maintain it; cover also issues
related to daily operation and management
- Contain advice for
estimating total costs involved in applying
the technology
- Contain consolidated
good country practices in introducing
and applying the technology
- The Working Party took
note of the offers by the contributors to
provide the coordinators with the section
inputs by 5 April 1999, and urged other members
of the Working Party to provide inputs and
suggest useful references to the contributors.
- It also noted that
the overall coordinators of the guidelines
had the possibility to approach the secretariat
with proposals to engage technical editors
to assist them in compiling various inputs
and editing the guidelines. It further
took note of the offer of New Zealand to undertake
the coordination work of the preparation of
the guidelines on the application of new technology
to population data dissemination data dissemination
under a consultancy and the offer of Singapore
to backup on the same basis, should the arrangement
with New Zealand fall through.
- The Working Party emphasized
the need to have the complete versions of
the three guidelines as well as the reports
of the case studies of the three pilot projects
as soon as possible. Those documents
should be circulated to the members of the
Working Party by the first week of June 1999
so that they could be reviewed efficiently
in the next meeting of the Working Party.
- In reviewing the results
of the survey conducted by the secretariat
on application of IT to population data, the
Working Party noted that it provided valuable
information and an useful analysis of the
state of IT application in the region.
The secretariat document revealed a wide gap
between developed and developing countries
in applying information technology, and again
confirmed the importance of achieving the
project objectives. The Working
Party recommended that the three guidelines
to be prepared under the project should take
into account the survey results and focus
on the apparent needs of the developing countries.
Nevertheless, the considerable progress made
by NSOs in applying IT in their latest censuses
and surveys allowed the Working Party to take
an optimistic view that developing countries
were able to seize many opportunities offered
by new IT.
|
|
| Recommendations
arising from technical papers presented in the
meeting |
- The Working Party praised
the quality of the contributed papers made
available to the meeting and noted that they
formed a significant repository of applied
technology information that should be made
available in formats required by the developing
countries.
|
|
| Recommendations
regarding the future programme of work |
- The Working Party recommended
that an item be introduced on the agenda of
the November Working Group of Statistical
Experts to discuss the outcome of the activities
of the Working Party.
- In view of the delays
occurred in delivering several project outputs
and the need to close the project account
by the end of the current UNFPA project cycle
(1999), the Working Party emphasized the importance
of expediting the delivery of all project
outputs. It nevertheless noted that
the activities of the Working Party had already
started to generate multiplier effects in
helping countries to make technology choices
and successfully securing resources.
The Working Party felt that the target was
still achievable, although it had been made
more challenging by added project activities
by the Mid-Term Review (MTR) conducted by
the donor in July 1998.
- Noting that no newsletters
had been released and that the project Web
site had been established only very recently,
the Working Party urged the secretariat, despite
its resource constraints, to give a high priority
to making progress in that regard.
- In drafting the planned
guidelines, the Working Party noted the MTR
suggestion to prepare the planned guidelines
in a manner of manuals. However, it
noted that writing fully-fledged manuals in
the field of information technology was very
challenging and carried a high probability
of their becoming obsolete shortly after their
release. In that connection, it
further noted that the rapid evolution of
the information technologies and the availability
of related information through the Internet
had reduced their demand and supply.
- The Working Party welcomed
the introduction by the MTR of a training
workshop, tentatively in October 1999,
as a channel to make the project outputs available
to a wider audience, and recommended that
- The broad objective
of the Workshop would be to sensitize
participants to the opportunities that
modern information technology provided
in population data operations and to improve
the guidelines produced under the project.
- It should be targeted
at IT and statistical managers who had
influence on the selection of technologies
for census and survey operations
- apart from conventional
lectures, the participants should be given
hands-on opportunities and time to test
and study new applications
- Working Party members
should act as resource persons in the
workshop and would be responsible for
organizing vendor demonstrations in areas
they worked on
- the guidelines and
pilot applications be used among the training
material for the Workshop
- the workshop should
be held in a venue where participants
had new technology readily accessible
- the secretariat use
its own knowledge about the countries
and the results of the survey to choose
participating countries
- the resource persons
of the workshop to take into account the
survey results in preparing their inputs
and presentations
- The Working Party agreed
that the participants of the workshop would
benefit from product demonstrations by representatives
of hardware and software providers, but noted
that such opportunities should not be restricted
to particular organizations.
- The Working Party noted
the observation that the issue of developing
an awareness/training package (project activity
3.2) for promoting effective and efficient
utilization of IT in population censuses and
surveys needed reconsideration. It proposed
that SIAP should reorient the aim of the package
for the purposes of training NSOs in new technology
applications. The material developed
would be based on the outputs of the project,
among others, and be used in current and future
regional and national training courses.
The Working Party noted that SIAP would report
on the progress in the next meeting.
- The Working Party recommended
that the project outputs should also be made
available to a wider audience by disseminating
them on CD-ROM, and be used in national as
well as SIAP's institutional and outreach
training programmes.
- The Working Party confirmed
that its next meeting would be held in Manila
with the application of mapping and
related technologies as a theme. The
dates were tentatively set from 22 to 25 June
1999. Apart from contributed papers
on the theme by the Working Party members,
their organizations and other invited agencies,
the agenda would include the review of the
three draft guidelines and the outcomes from
the three pilot applications for which the
respective coordinators would prepare documents
well in advance of the meeting.
|
|
| Workshop
on the application of IT to Population Data |
| Duration |
| 7 Working days in October, 1999 |
| Participation |
| The project will support the participation
of : |
- 30 persons from developing
countries including the member developing
countries on the Working Party
- the coordinator of each
guidelines
- Two resource persons/
consultants
|
| Other countries on the Working Party
will be invited to attend at their own expense |
| Strategy of
the Workshop |
Day 1 - 2: Introduction
of IT in general (Consultant and secretariat)
On the second day the participant will
be divided into three groups where each guidelines
will be introduced. The groups will be formed
based on information from the survey and/or
their interest.
Day 3 - 6: Each group will be exposed
to a specific guideline, and will be asked
to discuss various issues involved based on
their experiences and comment on the content
of the guidelines. Each group will
produce its report. The coordinator of
each guideline will introduce their guideline
and lead the discussion .
ay 7: Three groups will get together
in the plenary to discuss each group report
and hold a general discussion. The final
output will be recommendations for revising
the guidelines and an overall report of the
Workshop.
|
|