Project timetable (revised 28 Oct 04)
Schedule Sequence of activities Comments
 
2004
 
May Submission of initial draft concept notes for TBPs  
29 Jul Inter-agency working group meeting  
6 Sep Submission of draft concept note/outline of the 2nd RMDGR  
6 Sep Submission of draft concept notes/outlines for the TBPs  
27 Sep UNESCAP/UNDP/ADB Steering Committee Meeting  
27 Sep Inter-agency working group meeting  
28-29 Sep Advisory Panel Meeting (First Session)  
15 Oct Submission of the revised concept notes/outline of the Report  
30 Nov Submission of input (1st version) for SG's report  
 
2005
 
7 Jan Submission of TBP key messages as inputs to the messaging workshop Inputs from all TBPs are requested
20-21 Jan Messaging workshop/brainstorming PMD to organize
11 Feb Submission of the draft synthesis note, chap III of the Report and key messages to Steering Committee for internal review  
18 Feb Submission of the draft synthesis note, chap III of the Report and key messages to Advisory Panel for review  
28 Feb UNESCAP/UNDP/ADB Steering Committee Meeting on MDGs  
1-2 Mar Advisory Panel Meeting (Second Session)  
10 Mar Submission of input (2nd version) for SG's report  
15 Mar Submission of relevant TBP case studies and key findings related to institutional change for inclusion into the Report Inputs from al TBPs are requested
18 Apr First draft of the RMDGR submitted to Steering Committee for internal review  
21-27 Apr Presentation of RMDGR key messages at the ESCAP Commission Session  
13 May First draft of the RMDGR submitted to Advisory Panel  
19-20 May Communication and dissemination strategy workshop PMD to organize
31 May UNESCAP/UNDP/ADB Steering Committee Meeting (review draft Report)  
31 May Inter-agency working group meeting (review draft Report)  
1-2 Jun Advisory Panel Meeting (Third Session)  
15 Jun Finalization of the draft RMDG report  
15 Jun Submission of the draft report for external editing  
15 Jul Completion of external editing of the report  
21 Jul Submission of the report to UN editor/printer  
25 Aug Completion of final proof reading  
25 Aug Final draft ready  
1st week Sep Launch of the 2nd MDG report  
     