
Seven broad thematic programmes, mainly on power infrastructure
and institutional capacity building, are outlined for the 9FYP.
Hydropower investment (implementation of major projects as industries
for revenue generation) is considered outside the plan. Skills development
and training programmes related to the power sector are included
in the National Human Resources Development Programme, being formulated
by the Royal Civil Service Commission.
The Power Generation Programme (Nu
180 million)
Domestic electricity consumption growth rate has been 9.53 per cent
per annum over the last five years. A growth rate of 7-15 per cent
(on average 12 per cent) is forecasted over the 9FYP period. To
cope with this growth rate, generation supply capacity of 10 MW
firm power has to be added annually in the local supply system.
This means that at least 75 MW peaking capacity has to be added
in the system to meet internal incremental demand within the next
five years. So the investment plan for power generation / supply
infrastructure has to cover costs of additional 50 MW firm power
during the 9FYP. A share of the budget can be invested as Government
Equity input in Mangdechu and/or Punatsangchu projects (about 10
per cent of total project cost) and a small portion (about 2 per
cent) for construction of 3 isolated micro/mini hydro plants in
remote areas during the 9FYP.
Feasibility studies of Gasa (150 kW), Sengor (50 kW), Tang (400
kW) and Sakten (200 kW) microhydro sites have been conducted during
the 8FYP for rural electrification of about 642 remote rural households.
Main parts of the Mangdechu and Punatsangchu projects will be reflected
outside the 9FYP as part of the economic development programme.
Equity budget provision can be invested initially to build up basic
infrastructure such as approach/access roads, bridges as well as
construction power required for the implementation of the incoming
mega projects.
The Power Transmission Grid Programme
(Nu 1,910 million)
To utilize the power generated by the Chukha, Kurichu, Basochu and
Tala projects and to extend the grid supply to meet the bulk power
demand of Dzongkhags and major industries, and to increase the reliability
of supply, it is necessary to extend the power transmission grid
network. Based on the demand forecast, it is proposed to build the
Tintibi-Trongsa/Bumthang transmission grid and the Basochu-Tsirang/Dagana-Gelephu
transmission network, to extend transmission lines and substations
to industrial estates, as being proposed by the Department of Industries
during the 9FYP as part of the mega projects under construction.
The Basochu-Semtokha line with transmission substation, and the
Malbasse 400/220 kV substation with associated Tala power lines
will also be built. Investments are estimated at Nu 1910 million
for this Programme. Based on the prioritised proposals submitted
by the Dzongkhags, it is proposed to extend grid power supply to
Gasa Dzongkhag (Nu 36.667 million) and other important Dungkhag
headquarters like Bhangtar and Lhamoizingkha (Nu 63.333 million).
After the commissioning of the Tala system and its integration with
the Chukha system, the Basochu system, and the integration of Kurichu
with the western grid, the system complexity will increase, proper
coordination and scheduling of events for optimum generation, transmission
and utilization of energy will be required. It is proposed to create
a National Load Dispatch Centre at Gedu or another suitable location
for economic load dispatch and coordination of power generation
and transmission activities (availability, load forecast, frequency
control) among the generating companies (Tala, Chukha, Basochu,
Kurichu), BPC (for in-country transmission and distribution) and
the Eastern Regional Electricity Board (Calcutta) and maybe the
northern grid of India too. This establishment will consist mainly
of dedicated real time data communication network laid in fibre-optic
cables including a SCADA, Information Receipt & Processing Centre
manned by a few engineers to coordinate the power system. This Centre
may be affiliated with the Druk Hydro Power Corporation in the beginning.
When it is formed, the Bhutan Power Trading Corporation can take
over the function. The suitable budget provision has been made accordingly.
The Power Distribution Programme (Nu 1,800 million)
During the 9FYP, utility functions shall be segregated from the
regular functions of the Department of Power. Electricity supply
and sales functions shall be corporatized and handled by a separate
autonomous corporate agency, BPC, responsible for micro/mini hydropower
generation, transmission and distribution of electricity, and for
electricity business in Bhutan. This corporate body shall be incorporated
in the Company’s Act and the Electricity Act of Bhutan. The
corporation shall buy electricity from generating companies, and
also generate electricity from isolated mini/micro hydropower stations
for distribution and sales to the consumers. Bhutan Electricity
Authority will be created under the Electricity Act 2001 as the
regulating agency of the Government to ensure that electricity business
is carried out in a safe and sustainable manner. Activities in the
following areas shall be carried out within the Power Distribution
Programme during the 9FYP period:
(i) Rural electrification
(ii) Urban electricity
extension services in Phuntsholing
The budget for the 9FYP shall be made available by the Government
to enable BPC to carry out the above activities besides its regular
functions.
To achieve the mission target, keeping in view the vision 2020 of
100 per cent electrification, it is planned to electrify 15,000
households in 20 Dzongkhags through extensive rural electrification
programmes estimated at a cost of Nu 1500 million through grid extension
or isolated micro hydropower development. Besides, sub-transmission
and distribution activities will be carried out to extend and upgrade
the existing urban electric power supply infrastructure in Phuentsholing,
where urgent need is felt. The existing power supply infrastructure
of Phuentsholing from 1965 needs rehabilitation. A tentative budget
of Nu 300 million (US$ 6 million) is proposed under this scheme.
The Operations and Maintenance Division, in consultation with the
concerned electricity supply section, will prepare detailed programmes
for implementation.
To achieve the RE targets, it will be absolutely necessary to contract
out rural electrification. While about 30 per cent could be undertaken
by BPC, around 70 per cent will have to be contracted to private
parties. This will allow simultaneous execution of the works, and
will enable acceleration of the RE programme. This will mean a deviation
from the conventional method, where only the Department of Power
and the communities in question are involved. This new approach
being proposed will also help the private sector to grow and increase
employment opportunities.
The Power Transmission and Power Distribution Programmes will be
implemented by BPC. The Government will provide the total budget
outlay for the Programmes as a capital investment to BPC on work-order
basis.
A budget of Nu 1,500 million (around US$2,000 or Nu one lakh per
household) is proposed for the RE programme. Detailed household
and village site surveys in each proposed geog will be done in consultation
with the Dzongkhags for implementation of the programme. Donor/Lending
agencies may ask for further techno-economic and social studies
of schemes before funds are sanctioned and approved. This extensive
programme will require active participation of the end-users as
well as the implementing agencies. Since the plan is very ambitious,
private sector participation shall be necessary to augment the existing
institutional capacity of the implementing agencies.
Institutional Capacity Building Programme (Nu 375 million)
The present functions of the Department of Power will be unbundled,
and the Bhutan Electricity Authority, BPC and the Department of
Energy/Power will be created in the 9FYP period. A new Ministry
for Energy and Water Resources is also expected to be formed. Corporatization
plan for BPC is ready, and this corporation will start functioning
from July 2002.
Under the Programme, techno-economic feasibility studies, water
and energy resource plans, update of power master plan (NORAD),
RE master plan, policy guidelines, electricity rules, technical
standards and codes shall be developed. It is proposed to carry
out feasibility studies of two or three major hydropower projects
(the Diglai project across Bumthagchu in Zhemgang, the Rothpashong/Kholongchu
in the east, and/or the Punatsangchu phase II) during the 9FYP.
A budget of Nu 375 million is proposed under this Programme. The
Programme is aimed at institutional capacity building in technical,
financial, legal and managerial aspects of the sector.
The Alternate Energy Programme (Nu
200 million)
An integrated approach planning for optimal and sustainable use
of available energy resources, based on short term, medium term
and long term demand forecasts is necessary as energy is an important
input for the economic development of the country. The electricity
sector is attached with high importance today because of its obvious
impact on the economy. However, import of fossil fuels, the transport
sector's high reliance of fossil fuels and the sustainable yield
of biomass to meet primary energy needs of the rural population
are also important issues. The affect of global warning due to release
of greenhouse gases from fossil fuel and biomass combustion are
issues of concern, too. Energy efficiency improvement is an appropriate
stepping-stone. Energy efficiency standards concerning technology
and process have to be chosen taking the above concerns into consideration.
Under the Alternate Energy Programme, biomass, solar and other alternative
energy programmes or projects, including management, technology
and energy efficiency sub-programmes, shall be carried out. An integrated
Energy Master Plan is expected to be developed under the Programme.
Solar water heaters, solar dryers, solar lighting, and improved
efficiency biomass stoves will be demonstrated. Private sector shall
be encouraged to participate to enhance the energy efficiency programme.
Consumers' and traders' awareness campaigns can be launched to promote
clean energy and utilization of efficient energy technologies and
cost savings. Studies can be carried out to find out possibilities
for replacement of polluting (global warming) energy by renewable,
clean, environment-friendly energy resources and conversion technologies,
and pilot projects can be launched. For example, pilot project to
demonstrate electric buses or fuel cell technology can be introduced
in and around the capital and Phuentsholing to study the possibility
of reducing fossil fuel consumption.
Besides the above mentioned projects, if additional funding can
be secured through grant assistance for investment in infrastructure,
projects to support renewable and environment-friendly energy technologies
for rural development and to promote socio-economic development
activities, would be welcome and be included under the Alternate
Energy Programme during the 9FYP. Therefore, the limited budget
provision is subject to revision depending upon the availability
of funds during implementation. Feasibility studies and project
documents will justify such extension of the Programme.
Private Sector Participatory Programme
in Hydropower Development (Nu 35 million)
To increase the capacity of the hydropower sector to undertake the
various stages of implementation from planning, design, and construction,
to operations and maintenance, private sector participation is felt
necessary as the existing institutional capacity of the Department
of Power and its associates is limited.
To enhance the institutional capacity of the private sector for
various development activities, a separate programme is planned
during the 9FYP.
In the past, the private sector has been involved mainly in the
supplies of electrical construction materials (trading) and transport
of goods. Lately, construction contracts are being awarded for the
building of power projects' infrastructure such as buildings, roads,
and water supply. Very recently, works have been awarded for the
construction of power plants (civil works in Basochu and Kellungchu
Hydel). To date, staff of the Department of Power has installed
most power distribution, e.g. rural electrification. In the 9FYP,
implementation capacity has to be doubled to achieve the planned
target of electrifying 15,000 households in 5 years. Private construction
companies would have to be employed to ensure timely implementation.
Therefore, the power sector seriously encourages real participation
of the private sector during the 9FYP by creating enabling environments
for cooperation.
A study will be carried out under technical assistance financing
from ADB to identify possible areas for private sector participation,
to formulate guidelines, rules and regulations and terms of reference
for private sector engagement. Conceptually, it is felt that the
private sector can be actively involved in the following activities
during the 9FYP:
(i) Rural electrification
(execution);
(ii) Options for privatization
of the Central Maintenance Section, Begna and its small transformer
manufacturing unit;
(iii) Participation
in hydropower plant development (build, own and operate (BOO), and
build, own, operate and transfer (BOOT) schemes as IPP's;
(iv) Study options
for and feasibility of power distribution services for community
operations (e.g. city corporation to monitor utility services in
town), and private sector participation in billing and collection;
(v) Entrepreneurial
skills development and training of community electricians, wiremen
and linemen for self-employment in internal wiring, repair and line
construction/maintenance contracts.
Major economic development projects
and programmes outside the plan
Tala hydroelectric project of 1,020 MW capacity, construction of
which started under the 8FYP, will be completed and commissioned
in the 9FYP period. Most of the electromechanical plant and equipment
will be installed during the second half of the 9FYP. The project
is anticipated to be commissioned in 2004 or 2005. After commissioning,
it is expected to generate more than 4,924 MU per annum.
The total costs of the project are estimated at around Nu 43 billion.
The project is being financed by the Government of India (60 per
cent grant and 40 per cent loan at 9 per cent interest rate, payable
in 12 years).
Basochu Lower Stage of 40 MW installed capacity estimated at capital
cost of 553 million ATS (Nu 1659 million) is expected to start in
the beginning of the year 2002 and complete in the year 2004. It
will generate 186 MU per annum when completed, and augment supply
in the western system. Project costs of 430 million ATS are financed
by the Government of Austria at 2.786 per cent interest rate payable
in 20 years (5 years grace and 15 years repayment). In addition,
123 million ATS is required for financing the construction of 35
km's 220 kV line between Rurichu and Semtokha, and a 70 MVA, 11/220
kV switchyard at Rurichu.
It is tentatively planned to invest in the construction of Mangdechu
hydroelectric project, 360/600 MW, in the Trongsa Dzongkhag, and
in the Punatsangchu project of 870/1000 MW in Wangduephodrang as
the major economic development activities for export of electricity
under the 9FYP. As part of an equity investment based on principles
of cost and risk sharing, it is planned to invest at least 10 per
cent of the project cost from the Government's side as equity input
mainly for the pre-construction activities such as project access
roads, construction power, and other. These two mega projects can
be completed during the 10th Five Year Plan period, if implementation
begins under the 9FYP.
It is anticipated that expenditures of at least 60 per cent of the
project costs will be spent during the 9FYP for Mangedchu Project
and 40 per cent for Punatsangchu. During the 9FYP, 50 per cent and
30 per cent external financing in the form of grant and a loan are
required for investments in Mangdechu and Punatsangchu, respectively.
|